Hi,
I am trying to automatically firm orders in a horizon in PPDS using the program /SAPAPO/BACKGROUND_SCHEDULING but I see that orders are not firmed. Can you tell me if I am making any mistake?
Here are the parameters:
Program : /SAPAPO/BACKGROUND_SCHEDULING
selection screen parameters:
Planning version: 000
Time profile SAP001
propagation range: SAPALL
Function/Heuristic: Firm Objects
Time profile: SAP001
Planning object: orders
Selection of orders for processing in step01:
Location: A012 (our location)
Product: 3451245 (our product)
When I run this, I don't see any of the planned orders that were previously planned getting firmed. Am I doing a mistake or are there any other settings that I am missing? Please help.
Thanks