Hi All,

I have done overall budget for my project and when I am doing financial posting it gives me an error budget exceeded. the budget exceeds by the same amount to do the posting. Budget is available for WBS and there is no assigned values for the WBS.

We are not using budget Release in our project.

I also checked with tolerance limit configuration and also tried CJBW and CJBN.

Is there any possibility that some authorization is missing when assigning roles from the BASIS team.

Thanks and regards

GVK

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Maria Terence Nov 15, 2016 at 09:08 AM
0

Hi,

Did you check your Project / WBS whether budget profile is assigned ?

Terence

Share
10 |10000 characters needed characters left characters exceeded
G V K K Nov 15, 2016 at 11:15 AM
0

Hi Maria,

I have checked even the budget profile, it is assigned to project profile and also its seen in the control tab of teh Project definition.

Budget profile has overall ticked.

Regards,

GVK

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi,

Did you report S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned whether the Budget is available, can you share the screenshot of this report

It should be some problem related to Budget assignment, try to go to CJ30 and check for the Budget and do Total up to see any errors you get.

Regards

Terence

1
G V K K Nov 17, 2016 at 06:18 AM
0

Hi Maria,

Thanks for your reply, I have solved the issue, It was a config issue, overall in AVAC was not ticked . Issue resolved.

Thanks and regards,