Budget exceed error while financial posting f-02 against WBS

Hi All,

I have done overall budget for my project and when I am doing financial posting it gives me an error budget exceeded. the budget exceeds by the same amount to do the posting. Budget is available for WBS and there is no assigned values for the WBS.

We are not using budget Release in our project.

I also checked with tolerance limit configuration and also tried CJBW and CJBN.

Is there any possibility that some authorization is missing when assigning roles from the BASIS team.

Thanks and regards

GVK

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Nov 15, 2016 at 09:08 AM

    Hi,

    Did you check your Project / WBS whether budget profile is assigned ?

    Terence

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Nov 15, 2016 at 11:15 AM

    Hi Maria,

    I have checked even the budget profile, it is assigned to project profile and also its seen in the control tab of teh Project definition.

    Budget profile has overall ticked.

    Regards,

    GVK

    Add comment
    10|10000 characters needed characters exceeded

    • Hi,

      Did you report S_ALR_87013558 - Budget/Actual/Commitment/Rem Plan/Assigned whether the Budget is available, can you share the screenshot of this report

      It should be some problem related to Budget assignment, try to go to CJ30 and check for the Budget and do Total up to see any errors you get.

      Regards

      Terence

  • avatar image
    Former Member
    Nov 17, 2016 at 06:18 AM

    Hi Maria,

    Thanks for your reply, I have solved the issue, It was a config issue, overall in AVAC was not ticked . Issue resolved.

    Thanks and regards,