Hello Experts,

we are trying to substitute constant value for movement type when PCA distribution cycle is executed 4KE5.

Substitution name "TEST"

prerequisite GLU1-RACCT = 'ABCD0000'

if met then substitute movement type = 'XXX'

in 4KE2->Extras->substitution have maintained "TEST"

everything is fine, have put trace and substitution is being called.

but we are expecting it to update movement type in PCA document -- but it is not updating, it is updating value in GLU1-BWART. not sure where to check this.

now the question is, if there is a way to substitute movement type field when PCA distribution is executed ?

Thanks & Regards,

Keerthi.

0 Kudos

Hello Experts,

i am still waiting for your response,

Thanks & Regards,

Keerthi.