Planned delivery time

Former Member
0 Kudos

Hi All

I am maintaining scheduling agreement for external procurement part numbers,at the same time i am maintained info record source list also, here my prolblem is am maintaining planned delivery time in scheduling agreement as 5 days.

Here my requirement for the external procurement part numbers is 27.06.2009,for this requirement i am running MRP so system is throughing schedule line on 27.06.2009 but as per schedule system as to through on 22.06.2009 because planned delivery time s 5 days but it is not happening.

But in PR case it s coming correctly.Kindly help me out to solve the issue

Regards

P.Srinivasan

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

ok

Former Member
0 Kudos

Hi,

check the lead time scheduling whether using in the ATP check.have the tick mark against in the field

check without RLT IN TXN: OVZ9

Anupam1143
Active Contributor
0 Kudos

Hi

I think when you are making schedule line for date 27.06.09 and the planned delivery time is 5 days so when the material is required on 27.06.09 then the PR should be fired before 5 days so that it can be delevered upto 27.06 .09 according to planned delivery time.

Hope it will clear to you.correct me if i am wrong

Regards

Anupam Sharma

Former Member
0 Kudos

Hi All

Thanks fo ur reply, I maintained planned delivery as 5 days so when i am creating purchase requistion system is proposong release data and delivery date.In my PR release date is 5 days before delivery date.

At the same time i am creating schedule line system is proposing only delivery date.Here delivery date is requirement date so system is not proposing release date.

Regards

P.Srinivasan

Former Member
0 Kudos

hi,

Please check the stock of the material..i think the stock is existing...and the PR is raised as per the reqmnt..

Regrds,

Sravanthi