Jun 22, 2009 at 11:27 AM

Planned delivery time

25 Views

Hi All

I am maintaining scheduling agreement for external procurement part numbers,at the same time i am maintained info record source list also, here my prolblem is am maintaining planned delivery time in scheduling agreement as 5 days.

Here my requirement for the external procurement part numbers is 27.06.2009,for this requirement i am running MRP so system is throughing schedule line on 27.06.2009 but as per schedule system as to through on 22.06.2009 because planned delivery time s 5 days but it is not happening.

But in PR case it s coming correctly.Kindly help me out to solve the issue

Regards

P.Srinivasan