Dear All.
In Construction Process our client is building 4 floor in that the main
Project is L1 WBS and in the
2nd level WBS will be Basement , Floor1 Floor 2 Floor 3 and in
Each Flat will will be separate WBS
My question is How to map Activity carried out in Floor level EG in Basement, Floor 1 2,3.
Re grads
raj