Dear All,
We know Assigned value in the Report : 13558 is = Commitments + Actuals + Remmaning Order Plan
But where can I find out the rem order plan value ?
If Rem order Plan = Total planned costs - ( Commit + Actuals)
But the figures are not matching
folloiwng are the figures Can anyone plz explan
Planned Costs : 10166262.9
Commitment : 1583389.04
Actuals : 7237161.95
Remenaing order plan: 7528515.27
My budget is over shooting where do I find rem order plan costs line items wise.
regards,
C S
thanks!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
do you have dependent objects attached to the WBS (like production orders)?
The remaining order plan should be the sum of the planned values in these dependent objects, minus actuals that were confirmed already...
hope it helps,
best regards,
Luis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
As per my understanding
Rem Ord Plan = The cost occur in internal activity + cost plan activity (or any one activity)
which are items are not directly called as commitments are called as Rem Ord Plan.
Thanks
S.Murali
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
remaining order plan value is the value from the network activity created PR values.
The PO value is less than the PR Value.
Edited by: AP on Jun 22, 2009 11:00 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.