cancel
Showing results for 
Search instead for 
Did you mean: 

Rem Order Plan

Former Member
0 Kudos

Dear All,

We know Assigned value in the Report : 13558 is = Commitments + Actuals + Remmaning Order Plan

But where can I find out the rem order plan value ?

If Rem order Plan = Total planned costs - ( Commit + Actuals)

But the figures are not matching

folloiwng are the figures Can anyone plz explan

Planned Costs : 10166262.9

Commitment : 1583389.04

Actuals : 7237161.95

Remenaing order plan: 7528515.27

My budget is over shooting where do I find rem order plan costs line items wise.

regards,

C S

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

thanks!

luis_rocha2
Explorer
0 Kudos

Hi,

do you have dependent objects attached to the WBS (like production orders)?

The remaining order plan should be the sum of the planned values in these dependent objects, minus actuals that were confirmed already...

hope it helps,

best regards,

Luis

Former Member
0 Kudos

Hi

As per my understanding

Rem Ord Plan = The cost occur in internal activity + cost plan activity (or any one activity)

which are items are not directly called as commitments are called as Rem Ord Plan.

Thanks

S.Murali

Former Member
0 Kudos

hi

remaining order plan value is the value from the network activity created PR values.

The PO value is less than the PR Value.

Edited by: AP on Jun 22, 2009 11:00 AM

Former Member
0 Kudos

My planned costs should never come more than assigend ?

I think there is some problem in the report!!!

Is there some way to run a program to re generate the same.

regards,

A S

ansar_shaikh2
Contributor
0 Kudos

I think ur customization relevant to controlling is not proper, bcz this cost is updated via controlling.

RU seeing year-wise (Remainder from 2008,2009....)???

ask ur FICO person to adjust the setting.

Regards,

ANSAR