Former Member
Jun 19, 2009 at 05:42 AM

planned order dates

133 Views

Dear PP Gurus,

I have one query regarding Planned order dates, I have kept 5 days as planned delivery time and GR processing time as 1 day in material master for packing material. I have run MRP where i have set to create planned orders for RM,PM........ After running MRP, when i checked dates for above PM, it is giving order start date as 22.07.2009 and order fin. date as 29.07.2009, so it is considering 7 days.

After that i have change planned delivery time to 3 days and again checked, now this time it has given order start date as 22.07.2009 and order fin date as 27.07.2009, so it is considering 5 days.

My query is from where it is taking 2 days extra every time? please guide.

Thanks in advance

kailash thakkar