Dear PP Gurus,
I have one query regarding Planned order dates, I have kept 5 days as planned delivery time and GR processing time as 1 day in material master for packing material. I have run MRP where i have set to create planned orders for RM,PM........ After running MRP, when i checked dates for above PM, it is giving order start date as 22.07.2009 and order fin. date as 29.07.2009, so it is considering 7 days.
After that i have change planned delivery time to 3 days and again checked, now this time it has given order start date as 22.07.2009 and order fin date as 27.07.2009, so it is considering 5 days.
My query is from where it is taking 2 days extra every time? please guide.
Thanks in advance
kailash thakkar