MRP Control of a Material

Former Member
0 Kudos

Can we control planning for a material in such a way that it should be planned for some sales order items while some other sales order items having same material must not be planned. This has to be controlled on a sales order item status. if the status is true, then only MRP should happen for that sales order item. we are using only MD01 for carrying out MRP.

we have got this situation and looking for some solution to this. Do share if you have some ideas in this regard.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

Try in MD50 where u can run MRP for each (sales order) line item wise

Regards

Brahmaji

Former Member
0 Kudos

Hi,

In your sales order in items detail screen you can set if the schedule line is relevant for MRP or not if am right you need to change from CP to CN.

Hope the above resolves the issue.

Regards,

Vivek