Cycle Count Setup Issues

Former Member
0 Kudos

I'm trying to setup a Cycle Count program in SAP (transaction code: OMCO). Every function I try to initiate brings up the same error... "Date 00/01/2009 cannot be converted. (Correct this)"

Step-by-step, what can I do to correct this error?

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

JL23
Active Contributor
0 Kudos

what did you enter when the error occurs?

JL23
Active Contributor
0 Kudos

I guess you have not assigned a calendar to your plant

Former Member
0 Kudos

How would I go about setting up a calendar for my plant?

JL23
Active Contributor
0 Kudos

calendar setup is done in SCAL

But then you have to assign the calendar to your plant.

This is in IMG > Enterprise structure > definition > logistics general > define plant