In one material base unit of measure is m2 and the production unit is PC.Now I want to create PIR for this material with PC(Production unit).How I can do this.

Regards

Amitava

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Amitava,

This is not possible in standard SAP.

You can create the PIR's only using the base unit of measure.

Already so many threads has been posted regarding the same issue.

Check and revert back.

check this link,

Regards

Mangalraj.S

Edited by: Mangalraj.S on Jun 17, 2009 4:28 PM

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Amitava,

u can not create PIR for the material other than the BUM. If your prod. unit is different also, you have to maintain unit relation in material master additional data, production unit in WS view.

for details please refer the thread, in this i explained clearly

sree

Former Member
0 Kudos

Hi,

Agood reply from the member