Push Production in PPDS

Hi Experts,

We have a scenario were there are 2FGs(Finished Goods) using the same SFG(Semi finished good).We have a excess of 500 in SFG.

While ding push production,

1. Is it possible to partially push the excess quantity to both the FGs ?

2. In case there are multiple excess orders in SFG which needs to be pushed , can it be done in a single go? currently we are able to push one order at a time.

3. Ones pushed we believe that the dependent demand is created as soon as raw material is available.

Please help clarify our questions.

Thanks,

Rajan.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Dec 14, 2016 at 10:16 PM

    Hi Rajan,

    It's only possible to push one receipt at a time, but it is possible to partially push the excess quantity to both finished goods, as long as 1 receipt at a time is generated e.g select one source of supply and push 250, then select the second source and push the other 250.

    I've played around with it and created a simple wiki with my tests, though most likely you're familiar with everything there: https://wiki.scn.sap.com/wiki/x/O4M5Fg

    Regards,
    Tiago