HR Mini Master

Former Member
0 Kudos

HI,

I am using HR Mini Master.I have assigned 4 person in my Work Center. and Now i want to plant these persons . for that suppose i have to assign 2 persons in single operation in pm order for ovehauling for 5-5 hrs, and similaliy another two in other pm operation. How can i allocate it. Like: splitting Individual Capacity in PM order and then capacity lveling.

(2) IN pM order dates can be schdul , but how i will schedule the time if i want to schedule my opration from 13 pm , whhile earliset date and time capture from work center.

Accepted Solutions (0)

Answers (1)

Answers (1)

peter_atkin
Active Contributor
0 Kudos

GAURAV_SAP

- Enter some time in an operation using a work centre with assign HR capacities

- Double-click on the operation number to enter the detail screens

- At the bottom of the screen should be 3 sub-tabs, select the Reqmnts Assignment tab

- Enter you HR capacities here including date/time

PeteA

Former Member
0 Kudos

Yes, Pete i am doing the same thing , but i am not getting requirement assignment tab..waht may be the reason . that tab is coming when i am using ind capacity but during person with hr , req assignemnt tab is not coming.

any formula in work center, config setting for wc or control key.

Former Member
0 Kudos

When i am trying to assign person in my order operation, which i attached in work center as hr master, during release of order,system showing "no capacity/not releavant finite scheduling, please guide me.

peter_atkin
Active Contributor
0 Kudos

What values do you have in the Scheduling->Capacity Header screen within your work centre.

Also what formula are you using on the Scheduling and Capacities tabs

PeteA

Former Member
0 Kudos

Hi,

"No reqmts/caps exists or not scheduling" error,

capacity header setup formula : SAP008 & capacity category 002 , scheduling tab : other formula :SAP004

and HR asignment done

peter_atkin
Active Contributor
0 Kudos

The standard settings for a PM/CS work centre are:

Capacities tab: Other formula = SAP008

Scheduling tab: Other formula = SAP004

Costing tab: Formula key = SAP008

PeteA