on 06-16-2009 5:30 PM
Hi,
After deploying ChaRM, if we refresh QA system with production server, would the projects be overwritten?
or Is there a way to perform system refresh without affecting CTS projects in QA?
Thanks and Regards,
Jamuna Nithyanandam
Hi,
normally CTS projects and IMG projects are created and maintained in DEV system, so a system copy PRD->QAS should have no impact. But I am guessing, your situation is a little different. If so, Could you please provide some details regarding your system landscape?
Best Regards,
Holger Slomka
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you for your reply. We have a normal 3 system landsacpe, however, during a normal refresh, we move delta transports (transports that moved to QA after prod restore date) manually.
When we implement how will we handle those delta transports, would we still move it manually and will this affect ChaRM in any way?
Thanks and Regards,
Jamuna Nithyanandam
What do you mean with "Delta transports"? I assume, delta transports contain those objects which were not moved to production, only to QA, and therefore the are now missing in QA after system copy.
CHaRM process supports to move all changes controlled into Production, by using normal corrections (transaction type SDMI). So there should no delta transport be required. If something was in QA and not on Production, when you perfromed the system copy, you can use test transport functionality, to re-import these missing transports into QA.
Regards,
Holger Slomka
User | Count |
---|---|
84 | |
23 | |
11 | |
9 | |
8 | |
5 | |
5 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.