PM -CATS

Former Member
0 Kudos

HI,

I am using HR mini master for my client, where i will maintain information related to preson . but these are contractor labour.I want to know about cats.

(1) First i need to pay them at the end of month day basis + Ot hours aginst any PM order.

(2) I have to assign these persons to PM order , Suppose two person req for an operation using Person basis . Then i have to do planning & manpower management also(Like individual capacity planning).So How can i do it.how cats is useful in PM. please guide me step by step process.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Garav,

1. You can create a separate work center for your contract labour ...

2. In CAT2 we can enter actual time .. you need to maintain proper data entry profile also in SPRO ..

3. In CAPP you can approve the time sheets ..

4. In CAT9 you can transfer the time sheets to plant maintenance .

Thus all the actual work gets captured against the work center and thus you can follow the process of contract labour in PM ..

Regards,

pushpa

Former Member
0 Kudos

Hi, thanx

But how can i split my person in any PM order against an operation for planning Purpose. What i need to assign in work center. Means suppose for example :

(1) In my work center 3 persons .For overhauling of an equipment i need two person name X and Y , i have to assign both for that operation in PM order for Z hrs. and third i will assign it to other operation. I need to plan them and also pay them.

For example : above scnario : i will make it one work center , assign two capacities, assign in PM order in Req assignmnet tab and split it. so that i can do the planning and levelling also.(CM07 and CM25). for payment i will create service master for capacities and make PO and pay them using service entry . How can i use it using CATS (HR master).

Guide me.