cancel
Showing results for 
Search instead for 
Did you mean: 

Refrain user to copy network activity

Former Member
0 Kudos

Hi Experts ,

I have a very unusual requirement and need to your help to solve it.

REQUIRMENT : We have a project in CLSD status , and network and its activities are also in CLSD status. Now , if a user selects a network or network activity in the same project (CLSD Status) , and right clicks on it , he is able to copy that activity and paste that again into the project.

We have to stop the user from copying a network or activity of any closed project.

Please suggest how to overcome this issue ...

Thanks

Ajay

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Ajay,

As a standard SAP you can't create the networks even after TECO itself ( hence not possible even after CLSD as well)..Hence seems there is some problem with your system.. Pls check.

Regards

K Ramaiah

Former Member
0 Kudos

Solved by myself by using a BADI.

Answers (1)

Answers (1)

former_member201206
Active Contributor
0 Kudos

Hi Ajay,

In standard it is not possible to forbid user copy such activity.

Kind regards,

Zhenbo