PO approval tab

Former Member
0 Kudos

Hello,

After making all steps through customizing on relesase procedure on PO's, there's still no tab on me21n for the approval step.

Is there any other step for this tab to be opened? Can somebody please explain the process??

thanks in advance

Irem

Accepted Solutions (0)

Answers (7)

Answers (7)

Former Member
0 Kudos

Hi,

The release tab gets triggered in the PO based on the characterisitic values maintained in the release strategy and that which is being used in the PO.

For eg. The characteristic values maintained are Document type, NB

Purchase Group PX

Purchase Organization, PO1

When the PO is created with document type NB, Purchase Group PX and Pur Org PO1, the release strategy gets automatically set in the PO when saved

Regards

Merwyn

Former Member
0 Kudos

Hi,

For releasing PO, you need to use T-Code ME29N. I think you were expecting to release PO through T-Code ME22N. Correct me if I have misunderstood you.

Thnx,

SG.

Former Member
0 Kudos

Well, there's no approve tab on me29n t-code.

I guess I need to activate it from somewhere? from PO types or something like that?

Thanks again

Irem

Former Member
0 Kudos

Check the value u have maintain in classification in release strategy with that in PO like PO type, value etc.

Former Member
0 Kudos

Please let us know the process you have done in creating the R.S. in details.

regards,

indranil

Former Member
0 Kudos

in me21n , press "check " button before saving you will find "release strategy" tab.

after saving you can find this tab in me22n or me23n

Former Member
0 Kudos

Hi Soydan ,

Before proceeding ahead , at first check the release strategy created for errors under the below path :

SproMaterials ManagementPurchasingPurchase OrderRelease Procedure for Purchase Orders--Check Release Strategies

Also do check whether the values entered in PO match with characterstic values in Release Strategy.

Regards

Ramesh Ch

Former Member
0 Kudos

Hi,

You need to maintain the characteristic values for the release strategy in CL24N

Regards

Merwyn

Former Member
0 Kudos

The tab only appears on saving the document or when you check the document.

If the tab does not appear after saving also, go to cl20n, enter the class type, release group and release strategy - there should be green tick there, if it is red, please change.

Viral Bhinde