Skip to Content
0
Former Member
Jun 16, 2009 at 08:32 AM

BOM and Characteristic Value Assignment(Configuration) in Project Builde

101 Views

Dear Experts,

Iam working on PS-VC integration where I am assigning a KMAT material to an Activity under a WBS element.Iam able to configure the material there itself.But this is only possible if iam maintaining BOM explosion=None in the CU41(Config Profile).

But i wish to explode BOM at Project Builder.Please give me your best solutions.

I also wish to see the configuration while working on WBS bom. how is it possible? In case of OrderBOM iam able to see the configuration screen.

Thanks in advance

Shiju