Hi All,

I have a done initialization for 2lis datasource long back for 6 plants by filling the setup tables and ran the infopackage with out any selections in bw.and now daily delta's are running for that plants.so,now i got a requirement to get data for some new plant.so ,how should I proceed further to get data for the new plant, what steps should I take care as already data is getting loaded for the old plants?.

Appreciate your suggestions.

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

You will have to re-initialize your datasource, by adding the new plants as well.

Do an init without data transfer, and load data for the new plants using repair full request, after filling up the setup table.

With this, the old plants will not get affected, and from the next delta run, all the plants will be loaded to BW.

Hope this helps...

Former Member
0 Kudos

Hi,

You can create another infopackage for the init load for the new plants in the selection. It should work.

Bye