Hi Gurus,

(1)I have to maintain two shifts in work center, how can i maitain it and use it. any scenario.

(2) I have to use individual capacity planning,but individual capacities are not getting in cm24 during capacity levelling. another thing , suppose i assign ind capacity to an operation, when it get free.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

U can create two shifts in work center header. Go there and click interval & shifts. Create ur shifts with version. When u activate ur version that shifts will be active, otherwise ur standard version will be active.

I think CM24 should show ur individual capacity.

regards,

Rajesh

Former Member
0 Kudos

actaually my client want to manpower managemnt. can i do it using work force planning or capacity planning . how it works. how can i assign person no in operation.

Edited by: GAURAV_SAP on Jun 16, 2009 9:49 AM

Former Member
0 Kudos

How can i assign person related to operation,? how it works

former_member187991
Active Contributor
0 Kudos

hi

you can assign person no in the opeartion detail view.kindly check the operation details where you can specify the respective person no for whom work has alloted.But to reflect in capacity levelling then i think you have to create each person as one workcenter which you can see in the capcity levelling

regards

thyagarajan