cancel
Showing results for 
Search instead for 
Did you mean: 

ECC6 Upgrade and EHP 4 because of a CRM7 in the landscape?

Former Member
0 Kudos

Hi,

I am in the way to upgrade my SAP 4.6c system to ECC6.

In my overall landscape, I have a CRM 7 installed.

Do you believe I need to perform a simple ECC6 upgrade or a ECC6 upgrade including EHP4 SR1?

In other words, is it mandatory to go through the Upgrade + EhP4 because I have a CRM 7 around?

Thank you,

Chris

Accepted Solutions (1)

Accepted Solutions (1)

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

I think its better if you will go from SAP 4.6 c to ERP 6.0 with EHP4. It will save a lot of time..

As far as CRM 7 is concerned it does not have dependency on it...

Thanks

Sunny

Former Member
0 Kudos

Thanks for your quick answer.

Could you give me some examples when you say that it will save a lot of time?

I noted there is no dependencies with CRM 7.

Thanks,

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

according to my view upgrade from SAP 4.6c to ERP 6.0 EHP4 is easy because you can save your time in all preparation task that you to carry before starting upgrade as EHP upgrade itself takes time for preaprtion task....

also, you can reduce the downtime of your production environment if you will directly go to ERP EHP4..

As EHP4 takes significant downtime to upgrade the system ( also depends on hardware and database size)...

Also, you can reduce probablity of error free upgrade by carrying out one upgrade instead of carrrying out 2 upgrade (from SAP 4.6c to ERP6.0 then ERP6.0 to EHP4)...

Hope it clears to you...

Thanks

Sunny

sunny_pahuja2
Active Contributor
0 Kudos

Hi,

I found an interesting ppt from SAP the compares previous upgrade to new EHP upgrade..please go thorugh below link and i think it will solve your doubts...

https://websmp202.sap-ag.de/~sapidb/011000358700000623682007E

Thanks

Sunny

Former Member
0 Kudos

I agree with you, EHP 4 will shortest the overall plan and will ease and make fast future new functionalities. SAP provided a standard roadmap to ECC6 using EHP4 SR1.

Answers (0)