Guys, here is my scenario

We are using MTS and we drive the production through PIR's and we are batch managed currently.

Lets say I have 1 material (mat1), 2 customers (cust1 and cust2) and 2 batches (batch 1 and batch 2). batch 2 can be used only by cust2. lets say i have mat1 with batch 2 in stock and I have 500 ea. I dont have anything in batch 1. I need to enter a PIR to produce batch 1 and have to tell mrp to consider that, can we do that ?