Skip to Content
0
Former Member
Jun 15, 2009 at 11:40 AM

PI sheet

36 Views

Hai gurus,

1) I had created BOM( cs01)/Master Receipe(C201)/Resource(CRC1).

2) created new process instruction category using T.C = O12C and message category in T.C = O13C.

3) Control recipe destination is created using T.C = O10C.

4) Assigned the Process instruction in the Receipe phase.

5) PIR is created and MRP is done using T.C = MD02.

6) Raw material is procured and picked using T.C = COIK.

7) The planned order is converted to process order is released and phase is confirmed and GR is done.

My question is the created PI sheet is not reflected any where during order release and confirmation

That is T.C = CO53/CO54/ CO60 and CO67 could not be used.

I dont know where the link is miising.

waiting for the positive feed back.

Regards,

sekar chand

Edited by: sekar chand on Jun 16, 2009 6:24 AM