Dear all,
Can i use Task list in Break down maintenance order?
Yes you can use if set of operations are defined and if you are using this set of operation for such break down, Then dont find any difficulty.
Riyaj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
yes you can use any type of task list for break down order like equipment task list, functional location task list or general task list. To select the tasl list just go to the order header menu: Select EXTRA: Then select task list selection: there you have the options to insert task list in order.
Hi
Task list is a predefined/planned set of operations for an activity. A Brakedown is an unplanned event which occurs in a plant. so it is not adviseable to have a Task List. Otherwise you will end up having a lot of Master Data.
FYI
venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
yes you can assign task list manually from the menu bar.Extras>task list selection>
regards
thyagarajan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.