Dear all,
I met a weired problem. In our SRM 5.0, serveral shopping carts were approved, but only one of them showing the status Awaiting approval. All the data are the same except the material. This happens twice in three months. We use WS10000129 to approve the shopping cart. I checked some places:
A. T-code: BBP_PD. It shows as below.
HEADER I1015 Awaiting Approval
HEADER I1021 Created
HEADER I1038 Complete
HEADER I1106 Shopping cart ordered
Status STARTED
Statustext In Process
but the approval state is COMPLETED
I checked BBP_GET_Status2, it shows as below:
Batch program for updating status information for SCs as of Rel. 3.0
No Shopping Cart (REQUIREMENTS) Found with Status = Transferred
Batch program for updating status information for SCs as of Rel. 3.0
On the basis of the data, no changes possible
'
The following RFC destinations were called:
RFC Destination: Call result:
B. Working flow diagnosis is OK
C. SLG1: NO log found.
D. ST22: No short dump.
E. System Error: SC not in Table GT_LIST_HEADER
Anyone has any idea?
Thanks!
Edited by: haimei Wu on Jun 16, 2009 8:10 AM
Edited by: haimei Wu on Jun 16, 2009 8:18 AM