Dear Experts,
I'm facing a consulting issue w.r.t. MRP run. The scenario is as follows,
Location 1(warehouse01)
Item : FG01
BOM: FG01 whs:01
Line item BOM: RM01 whs:01
Location 2 (warehouse02)
Item :FG01
BOM: FG01 whs:01
Line item BOM: RM01 whs:01
RM01 is a purchase item and FG01 is make item.
we are using Single Database for the 2 locations thus One BOM for FG01
Scenario: If I have Sales Order for FG01 with Qty 10 for warehouse 01 and Qty 20 for warehouse 02, when I run MRP the recommendation result thrown is Production order for FG01 30 Qty for warehouse 01 and Purchase Order for RM01 30 Qty for warehouse 01.
Expected Result:
Production Order for FG01 10 Qty @ warehouse 01
Purchase Order for RM01 10 Qty @ warehouse 01
Production Order for FG01 20 Qty @ warehouse 02
Purchase Order for RM01 10 Qty @ warehouse 02
We are using SAP 2007A
Need your help to attain the expected result.
Thanks in advance.
Regards,
Aditya
Edited by: Aditya Rao on Jun 15, 2009 12:32 AM