I have some doubts regarding 0CDS_DS01 and 0CDS_DS02?

As we know , Schedule Lines for Sales Scheduling Agreements is for 0CDS_DS01

Sales Scheduling Agreement Items is for 0CDS_DS02 ,

the data of 0CDS_DS02 can only be filled with data about sales scheduling agreement items that are also planned in SAP APO.

it seems that 0CDS_DS01 is also from APO,

what is the difference between Schedule Lines and items ?

thank you very much

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Schedule line: The division of an item in a sales document according to date and quantity.

For example, if the total quantity of an item can only be delivered in four partial deliveries, the system creates four schedule lines and determines the appropriate quantities and delivery dates for each schedule line.

--> one item can have more schedule lines