Hi all
I want to work in ECC only with process orders, so I have created and activated the order model. The problem is that, I can't transfer the order from APO to ECC because of the system message: there is no planned order model.........if I active a model for planned orders, it woks, but then I have in ECC, both, process orders and planned orders.
Thanks