While doing automatic settlement to AUC assigned values changes for the WBS cost amount.
eg. WBS actual cost is 10,000 so before doing settlement Assigned value is 10,000 in CJ31
after running CJ88 assigned value in CJ31 changes to 20,000.
also in report S_ALR_...3558 for budget / actual in actual cloumn values changes to 20,000.
can anybody rell me why it is happening ? any config related setting is there ?
regards,