Activity price in Std Cost Estimate

40 Views

We are running the standard cost estimate. Everything in the estimate is correct except the Activity Price calculated.

We have maintained the price as 350 (Fix) + 20 (Var) for this activity (unit-MT) in KP26. But the price calculated in the cost estimate is 7 only. How come this reduced price in the estimate ?