Hi

I have a material HALB1 which is a BOM component to FERT1. The setting for both materials are PD, individual requirement 1 and lot size EX. I have 2 production orders for FERT1 against the WBS nos W-1 & W-2 with start date diffrence of 3 days . Now when I am running MRP, system is generating 2 different planned orders for HALB1. But the system should have combined together both the req qty into 1 and created a single planned orders. My setting for Reschedulling horizon is 999.

So where is the problem. Be remember that the req is project specific so I can not change the setting for HALB1 to collective requirement. But I want to combine together the qty for the WBSE and create single planned order within 999 days. Pls guide