Hello Experts,
For a process order & scheduling typr forward/in time if I take sat or sunday as a start date then if I click on schedule, system changes it to previous workin day (friday). But however if i select backward/in time scheduling type & put week ends as finish day then system does not change this date.
How can I make system to allow schedule start date on week ends also for forward/in time scheduling type. in a factory calendor sat & sunday are holidays. while for work center, calender sat & sunday are marked as working days.
Thanks for advance,