Dear All
Here an issue regarding WIP stock
1. One semi finish material having 4 operations , out of 4 operations,2 operations are completed before Go live ,remaining 2 operations has to be done after Go live
2. WIP stock as on cut off date is 100 pieces ,for 100 pieces, the raw material of 10 kg is issued.
Some body is suggested as raw material of 10 kg has to bring in stock, then order to be created for 100 pieces , raw material of 10 kg to be issued for that order ,confirmation to be done for first 2 operations the remaining 2 operations will be confirmed after Go live .
please suggest me in what way I have to proceed