Hello All,
I have created a workcenter with category as 'Labor' and in Workcenter 'Capacity' tab have defined the 'number of individual capacity' as 2, with operating time as 8 hr/day, making total capacity 16 hrs = 8 x 2.
I have assigned this workcenter to an activity on WBS element, and have defined duration of activity as 8 hrs. When the scheduling is taking place it is calculating 1 day to finish the work, whereas I was expecting .5 day to finish the work.
Somehow I did some more tests, it is not taking the ''number of individual capacity' into consideration. It is always using '1' as number of individual capacities.
Can someone kindly inform me how to fix this problem.
Thanks,
Sachin