BPM workflow not able to reflect the latest changes done.

54 Views

Hi.

I've a BPM instance in QA which got logically deleted after entering into exception block .

Now i've made necessary modifications (removing a loop and adding a Switch) in DEV and transported to QA (Repository) successfully. Now QA repository has the latest version of BPM.

Now in QA, I've manually triggered the BPM from http-client and i couldn't see the latest version of BPM in the workflow (PE adapter in SXI_MONITOR). I could only see the older version (with Loop) and hence it again went into exception block. I tried triggering thrice but in vain.

Where am i wrong? Do i need to transport the BPM in DEV Directory to QA Directory in order to reflect the change that i did?

Kindly provide ur inputs.