Hi,
In CA02 for a particular Operation, I do have a control key which is non-cost relevant. Later when I change the Control Key to a (costing relevant) one,
the value in Costing relevance field of the routing operation line does not get changed
automatically. Many times, user forgets to change it manually and that causes operations excluded from the costing process.
If the Operation is deleted and re-created, the value gets picked up from the new Control Key.
When a user amends an Operation with a new Control Key, is there a way in SAP to get this value changed according to the setup in Control Key master ?
Valuable responses will be highly appreciated.