Hi Gurus,

I have a concern while creating the PR for service activity. The service is planned as a service activity element within the network activity. The start & finish date for the Service activity element is being taken from the parent network activity.

Now in the PR, the Delivery date is being taken as the Finish date of the service activity element (or the parent network activity). For example: if the activity is starting on 1st June, and finishing on 31st Aug,

the PR delivery date will be 31st Aug and the same will be reflected in PO also. But actually the activity is to be started on 1st June. So how & when this delivery date can be changed to 1st june.

Regards,