on 06-10-2009 4:32 PM
Dear Gurus,
When we create a production order for Semi finished which is maintained with Moving Average Price(MAP) in material master and we do confirmation of the order with "CO15'.
My client wants after goods receipts against 101 movement type the price should be up date in Material; Master immediately.
Regards
RAM
closing this thread.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I think this cant be done.
> My client wants after goods receipts against 101 movement type the price should be up date in Material; Master immediately.
How much MAP should be after GR? From where this value will come?
The accounting entries are passed on the basis of price maintained in the material master. The MAP is the input to the business activity. So as per my understanding the MAP cant be updated with GR against a production order.
Also, the costing run would update the standard price, and wont be helpful as the indicator would be 'V' in material master.
Hope it clears.
Regards,
Rohit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi ,
let us say, semi finished components with MA price of 100/Pc and I have stock of 100.
I do GR with quantity 100 and that will be in the price of MAP 100/PC. So, my stock will go up to 200/PC with the price of 100*200.
There will not be any price change. Or tell me what sort of price chagne do u expect. Since ur initial price is not from BOM and routing (Bca u r using pricing control as V), there will not be any variance. So, do not expect any price chagne after every GR of PO.
Vijay
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.