Calculation of ord. finish date in Plnd order / Purch. requisition

Dear all,

I really need help to set up my MRP. I have this problem in planned order scheduling for the material provided with external procurement:

For example:

Date: 22.06.2017 -> start of production for a finished good. No float before on the master data, so the requirements for the connected raw material (the OrdRes line in MRP list) is in the same day, 22.06.2017.

I have set up 5 days for GR time (WEBAZ) on the raw material's materd data. So the Order finish (the delivery date) of the Plnd order should be 15.06.2016 (saturday and sunday are not work days).

Instead of this, the Order finish is on 13.06.107. It seems that the delivery date is anticipated by two days every time.

Where I find this setting? Which are the parameters that influence the calculation of the delivery date of an external procurement material?