Dear All,

I'm using backflushing. However, in CO11n I'm doing "Goods Movement", the planned quantity for material X is 1000 KG if I want to issue 1500 KG it will stop me and say material failed because it exceeds reservation quantity. How can I avoid that?

Also in COOIS I'm displaying the "components" list which should show me the required quantity for each order component and the actual issued quantity. It only displayes the PLANNED issued quantity and doesn't show the UNPLANNED issued (which I can see from the Documented Goods Movement), I find that very weird.

Any suggestions?