Dear all,

I want configure ECP.

plesae provide me step by step process.

Thanks in advance

Regards

SONAL

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jun 09, 2009 at 01:08 PM

    Pls refer this link, which shows ECP example. For configuration do normal config which you could do for Costing like Costing variant, planning profile etc.

    http://help.sap.com/saphelp_46c/helpdata/EN/84/442f38cac1f505e10000009b38f8cf/frameset.htm

    Sarang

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 09, 2009 at 01:44 PM

    Hi Sonal,

    ECP Config :-

    Step-1: - First Activate one CO-Version in Controlling Area for ECP.

    Step-2: - Plan Costing Varient required to Plan costs. Varient "PS06" available in Std SAP for ECP.

    Step-3: - Assign Costing varient to Plan Profile.

    Step-4: - Assign Plan Profile to Project profile.

    Step-5: - one Execution Profile with all required settings as per requirement.

    Regards,

    Hari

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      Continuation of what hari has explained

      Step 6: Create a Model for ECP.

      Regards

      Anish PV

      In continuation to what Hari & Anish said, use following T-code for creating costing models:

      CKCM - Models for Easy Cost Planning