POP-UP In PO & PR

Former Member
0 Kudos

Hi,

We are using PS Module.PR is generated thru PS only.now if we change the value of material in PR,system should give the POP-UP message "that material cost is more than projected cost:.

is there any standard functionality.

or we can use BAPI / user exit.

Regards

Pavan

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Pavan,

There is no std functionality available for generating pop up while changing price in System generated PR through Project Networks. but you can activate workflow for PR changes like price and req.date and qty.

regards,

Hari.

anishpv
Participant
0 Kudos

Hi,

Make the concerned filed in display mode to avoid any changes in price, or else use user exit to check the changes in values.

Regards

Anish PV

Edited by: pv on Jun 10, 2009 9:34 AM

Former Member
0 Kudos

If a PR is generated through PS, then you cannot change it though ME52N . All changes has to be made from PS itself.

Edited by: Devdut Saha on Jun 9, 2009 1:35 PM

Former Member
0 Kudos

while creating PO we can change the price of material.so can we restrict.

Former Member
0 Kudos

there are settings in MM while copying the details from PR you can make some of the fields as non-changeable. I think you can do it...

just check with the MM consultant..