DearAll,

We are using the scenario stock transfer between plants two steps.in the source plant we are issueing the goods with on 303 movement in MIGO with Remove from storage option. in the receiving plant we are receiving the goods with refernce to 303 material document in MIGO with place in storage option.

we are using the version SAP 4.7.

my problem is at the time of goods receipt SAP is allowing to the posting date less than the source plant 303 document date. it should allow the posting date as Greater than equal to source plant document date at the time of GR.

Any standard pracktise is there.

for example source plant 303 document date is 08.06.2009 wrongly i have entered the receiving plant 305 document posting date as 06.06.2009 it is allowing to post it is not throw any information. it should not allow to know.

i want to control this. any standard controls is there. kindly help.

Regards

P.Anandhakumar