Production order changes

Hi,

Here we have PP and PS , MM , HR module.Scenario is : some changes may happen in the design of a product even though production order for the same is released and goods are issued and some operations are already confirmed. How to map this?

I said to client that they can change their released production order eg addition or deletion of components and/or operations. But my client says they want a wok flow like email to be triggered to their manager about these components / operation change and those should first get approved from manager before proceeding further.

Please reply how to map this.

Regards.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Jun 08, 2009 at 06:52 PM

    HI Yasi,

    Tell your PP Consultant to Implement ECM (Engineering Change Management).

    Your Client requirement will be fulfilled.

    Regards,

    Hari Kishna K

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 09, 2009 at 09:37 AM

    Hi Yasir,

    SAP Business Workflow can be used for production order changes.

    Configuring work flow to many steps needs to be followed for that refer below link, refer page no. 22

    http://help.sap.com/printdocu/core/Print46c/en/data/pdf/BCBMTWFMPP/BCBMTWFMPP.pdf

    follow menu path for workflow

    Spro > Production > Shop Floor Control > Workflows > Production Order Changes

    refer below link to build workflow from scrath

    https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/e0bbdb3c-d640-2a10-d3b2-e4d9b90536a6

    For triggering workflow you need to take abap & basis consultant help

    Hope this will help you.

    Regards,

    Sandeep