Hi

I need to create a sales order where the unit of measurement for the ordered quantity differs from the unit of measurement in the pricing condition PR00. This works fine if you have a fixed conversion, because you can simply set up the conversion in the material master of the sold material. My problem is that this conversion is flexible and can be changed by the sales representative. How do I do this? I remember that this isn't a problem at all in MM-purchase orders, you simply enter the conversion in the conditions tab directly. That doesn't seem to work in sales. Any hints?

Example for spreading services for farming.

Sales order for service "spreading", order qty = 17.600 HA, price = 21.00 GBP per 1 KGH (kilogram per hectar), conversion = 17.600 HA = 723 KGH if 12.720 KG of fertilizer is spread on the field. Problem is that tonnage and the field size are changeable. As well the theoretical application rate of 723KGH can be overwritten manually as required.

thx

Bj

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Make sure the quantity conversion flags are checked, and then allow manual condition processing. This should open up the fields to allow for manual adjustment of the quantity relationship.

You will still need to maintain a default UoM ratio that will be proposed on the sales order, but that relationship will then be able to be changed at order entry time (or after save in change mode).

Bill Wood

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Bill,

great stuff, that was exactly what I was looking for.

thx