Hello planning community
I have a question on the exit planning function ( xth_data).
So fare I am very familiar to work with this exit function and able to change/create the planning data in all directions requiered by the client and the planning process.
However.... Up to date I didn't find a good way to read 'auxiliary' planning data (reference), that I need for calculation in the exit function without locking it. Thus up to date I have read all data into xth_data and therefore locked also all data (reference and transaction) because both are contained in xth_data.
So does someone have a good idea how to read reference data within the exit planning function framework and therefore not locking those data.
Thanks a lot for a good idea
Best regards
Christian