schdelung for externally procured material.

32 Views

Dear Gurus,

We have defined planned delivery time for externally procured material. After MRP run system is generating delivery dates for that.

We want if there is capacity constraint at supplier's end then how to handle this issue in MRP run.

Example -

PR generated after MRP run for XXX material code for 5000 kg and required date is 15/06/2009.

Supplier's manufacturing capaicty of this material is 500/day i.e. from today he will be produced only 3500kg.

In case shop floor plan will not executed due to shortage of supplies.

How to map this scenario in SAP so that MRP controller will come know that the said material will not be available on required date and he will have plan some thing else during that period.

Regards,

Abhay