planned order date and production order date

620 Views

Dear gurus,

I have a planned order with start date 1st June. I converted it to production order on 5th June. The production order start date has come as 29th May.

The scheduling is forward and float is all zero.

What can be the reason for the start date of the production order going back? How to see that the production order start date always comes on the date of conversion and never changes later?

Thanks and Regards,