Hi i have done following steps that lead me to a problem
1. MIGO of a material done with posting date of march
2. I have issued that material using mvt 281 Q to reservation with posting date in april
Now, since i have done above step-2 by mistake, because i wanted to issue the material in march, i have done following two steps.
3. I have cancelled the material issue document created by step 2 (Using MBST) above with posting date in march
4. I have issued the material using 281 Q agaist a reservation in march
Now the problem starts...System is showing the same material stock in March, which i dont want.
System is also not allowing me to issue the mateial in march as already i have issued once agaist the reservation (Step 4)
What should i do to remove that material from stock in march??