Dears,

We have set up Release Strategy with the following characteristics which is working fine:

1. PR Doc

2. Cost Center

Now the requirement is as follows:

1. The Dept Manager (cost center 12345) will approve all PRs related to this Cost Center.

2. His Deputy (Planning Section Manager) will approve those PRs which is related to his section (Planning Section), as well as the Dept Manager (above) will approve the PR. How can we map this.

When we use the PR creater ID, it is working fine with the second option, however it is not working with the first option (if we leave the creater ID blank).