Skip to Content
avatar image
Former Member

During the Quotation

Dear all,

Basically iam SD consultant. i got SD-PS integration

Requirement is:Iam getting 100 quotation per month.In this probably 5-10 Projects will be goes to Sales Order.So,during the Quotation it self i need to run the DIP profile.(Planned cost)-if customer satisfies with the Quotation ,then we are creating the Project in SAP.

How can i configure this.....?

Plz advise me on this...

Thanks in Advance

Regards

raj.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Jun 06, 2009 at 08:06 AM

    Hi Raj,

    Configure the DIP profile, define condition for product costing,

    Maintain order type parameters in Customizing in 'Define sales document types'

    Regards'

    Syed

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 06, 2009 at 09:30 AM

    u can plan cost in projects using Easy cost planning or unit costing.

    can convert the same as quotation by assaining the DIP profile.

    u can aslo use unit costing also for the same.

    ASK YOUR SD CONSULTANT, HE WILL DO THE DIP CONFIGURATION FOR YOU.

    Regards

    surya

    Edited by: surya pampana on Jun 6, 2009 12:38 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 06, 2009 at 10:51 AM

    Hi,

    I think it is better in your case to create a Quotation in VA21 and if approved from customer then only create a Sales order and a project.

    Muzamil

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      1. Define planning profile with costing variant PS06(ECP)

      2. Define DIP Profile (for Quot and SO)

      2.1 Usage of DIP profile ;Sales Document type

      2.2 Charateristics which determines the requiremnts (relevent/No summarition/single values/set name)

      2.3 Source ECP (100%)

      2.4 Selection criteria (source set name for each chartr)

      2.5 Material Detemtn (material no./tran qty+cost/)

      2.6 Criteria materil determn.(set name for charateristic which delivers cost,qty)

      3. chk settings for DIP prof --ODP2

      4 Assign DIP in Proj prof.

      5. costing model for ECP--CKCM

      regards

      Anish

      Edited by: pv on Jun 9, 2009 11:08 AM

  • avatar image
    Former Member
    Jun 09, 2009 at 06:48 AM

    Hi Venky Raj

    DIP profile should be set up by SD guy. Just ask your SD guy to do it.

    Add comment
    10|10000 characters needed characters exceeded